COMPLETED

Maple Park Playground Renovation

Start Date

April 03 2021

End Date

June 09 2021

About Project

On November 30, Maple Park Playground construction was officially postponed until 2022, due to uncertainty of the estimated delivery date for the playground equipment. The Village of Wilmette approved the necessary permits for Maple Park Playground construction

June 10, 2022
Completed
Renovated Sidewalk

The project is complete. Thank you for your patience during construction.

June 6, 2022
Restoration
Concrete for the Sidewalk

The concrete for the sidewalk has been poured and the formwork has been removed. This week crews will be onsite patching the asphalt, striping the asphalt, and landscape restoration.

May 26, 2022
Demolition
Sidewalk Imporovement

The crews have completed demolition and are starting to frame for the new curbing and sidewalk.

Download PDF