Public Hearing on December 9; Truth In Taxation
For details, check our Bulletin Board post below.
×
Public Hearing on December 9; Truth In Taxation
For details, check our Bulletin Board post below.
Public Hearing on December 9; Truth In Taxation
For details, check our Bulletin Board post below.
START DATE
Spring 2022
PROJECTED END DATE
Summer 2025
LOCATION
Langdon Park (Sheridan Road at Chestnut), Wilmette
The work at Langdon progresses. The revetment has been completed from the north property line to the haul road. The revetment on the south side of the property has begun as well. Ongoing deliveries of armor stone and other materials continue, and backfilling has started around the completed portions of the revetment.
View the project plans and additional information below.
In 2020, Langdon Beach was closed due to significant beach erosion. Since that time, the Wilmette Park District has been working with engineers from SmithGroup to analyze Langdon’s shoreline and develop solutions to protect the beach and bluff for future generations, and to build an access path.
The water levels in Lake Michigan receded in 2023 and the Park District opened a temporary path to the beach over the 2023 Labor Day weekend.
Following the temporary path work that was completed in 2023 to re-establish access to the beach at Langdon Park, we are now working to provide a permanent condition that will provide safe access to the water and protect the shoreline. This work, as shown in the Langdon Park Shoreline Stabilization Plan, will begin with:
The project began in early 2020, when erosion of the entire Wilmette Park District shoreline had become a significant concern, and Langdon Beach was closed due to safety concerns. At that time, the Wilmette Park District engaged SmithGroup to analyze the shoreline erosion issue and provide recommendations on revetment work to mitigate erosion damage.
The overall goal of the Langdon Shoreline Protection and Access Project is to preserve Langdon beach for future generations and provide safe access to the beach while preserving and enhancing its original natural character.
Langdon Beach is closed due to shorefront erosion and safety concerns.
Wilmette Park District engages SmithGroup to consult on shoreline conditions, including the Sailing Beach, Gillson and Langdon.
SmithGroup presents first study of shoreline erosion at Gillson and Langdon; Board agrees that preserving the bluff at Langdon was most urgent issue.
Park District directs SmithGroup to develop a plan for the protection and restoration of the bluff at Langdon specifically, including beach access.
SmithGroup completes a number of different studies determining vegetation and soil conditions on the bluff. They present their initial findings and different beach access proposals to the Lakefront Committee. Included were four styles, with different stair and ramp designs. Ramp and revetment options were fairly similar in price. The Committee leans toward Concept C, in which the path design provided not only access to the beach but also provided additional bluff stabilization.
Lakefront Committee decides on Option C, which after some modifications from the initial concept, was an ADA-compliant ramp across the face of the bluff, which also provided bluff stabilization in addition to the revetment. Stairs are added at a later meeting due to Park Board concerns that visitors would deviate from the path and trample down the bluff vegetation. SmithGroup engineers began the design and permitting process.
Community members attend meeting to express concern about the design proposal. The Park Board asks to revisit the original concepts as a result of community input.
SmithGroup presents to the Board to address concerns from the community. Board asks SmithGroup to refine and further develop concepts based on input.
Park Board and visitors from the community view Langdon presentation by SmithGroup. Board narrows access path design options down to B2, B4 and B5, and asks Park District staff to review the options and make material recommendations for use in creating the path.
Park Board asks SmithGroup to move forward with detailed designs for the B4 access path option.
Park Board asks SmithGroup to revisit temporary access options at Langdon prior to permanent access. Letters of No Opinion required by USACE and IDNR; the latter provides its letter.
SmithGroup presents to the Park Board and visitors from the community. Village of Wilmette asks the District to contact ICDB to determine if access path must be be ADA compliant.
ICDB confirms that ADA compliance is required for the permanent Langdon Beach access path. Clarification is requested about whether temporary access must also be ADA compliant. No response had been received.
SmithGroup presents final two long-term access path design options to Park Board.
Park District sends community survey to learn which design is preferred.
Park District staff presents access path survey results; Park Board examines accessibility issues. Final approvals for temporary access path are secured.
SmithGroup presents alternate path and material options, and Park Board receives presentation from ADA experts WT Group regarding ADA compliance.
On August 22, the District received the permit for the temporary path at Langdon and have confirmed the contractor will be onsite on August 30 to start the work. The project is anticipated to take approximately one week.
Board of Park Commissioners direct Park District staff to pursue path option ORA 2 in detail. SmithGroup will begin work on detailed drawings and plans.
SmithGroup presents a project update to the Board of Park Commissioners.
SmithGroup presents update on schedules and budget, staff shelter/beach access management structure design, park entry improvement options, tree survey
District staff and consultants from SmithGroup have secured final permits and construction begins Tuesday, September 3. The park and playground will remain open, but beach access will be restricted during construction.
The work at Langdon is progressing on schedule. The revetment work is complete from the north property line to the haul road. The revetment work on the south side of the property has begun. Ongoing deliveries of armor stone and other materials continue, and backfilling has started around the completed portions of the revetment.
“Commissioners back southern path down to Langdon” – The Record North Shore, September 12, 2023
“Temporary path gives public access to Langdon Beach for first time since 2019” – The Record North Shore, September 10, 2023
“Langdon Beach’s future still on hold as park commissioners push decision to September” – The Record North Shore, August 15, 2023
“Facing residents’ pleas for a quicker solution, Park Board reaffirms support for ADA access to Langdon” – The Record North Shore, July 11, 2023
“Langdon Beach could reopen in late summer under plan supported by park commissioners” – The Record North Shore, January 10, 2023
“Park Board takes step back on Langdon Beach stabilization plan” –The Record North Shore, Aug 9, 2022
“Langdon Beach future one of several topics for inaugural Committee of the Whole meeting” – The Record North Shore, July 1, 2022
“Wilmette’s Langdon Beach closed this summer due to shoreline erosion, rising Lake Michigan water levels” – Chicago Tribune, June 28, 2019
“Beach erosion could jeopardize swim season” – CBS News Chicago, April 25, 2018
”Shrinking beach may mean no swimming at Wilmette’s Langdon Park this summer” – Chicago Tribune, April 2, 2018
Photos
Join our list to stay up-to-date on all exciting and important things happening at the Wilmette Park District
Enriching the quality of community life through creative programming for people of all ages and abilities, while protecting open spaces and natural resources for future generations.
Quick LInks
Enriching the quality of community life through creative programming for people of all ages and abilities, while protecting open spaces and natural resources for future generations.
Enriching the quality of community life through creative programming for people of all ages and abilities, while protecting open spaces and natural resources for future generations.
Quick LInks
2024 © Wilmette Park District. All rights reserved.
Designed, Conceptualized and Developed by OnPoint Insights LLC