Solar Panel Project – Community Recreation Center
START DATE
2025
LOCATION
Community Recreation Center, Wilmette
Updated 10.31.25
Solar Panel Project - Update
The CRC Solar Project is nearly complete, awaiting final inspection and ComEd authorization to activate the panels. Solar Panels are expected to be live in the next few weeks.
We’ve put together a BLOG to help inform the community about the project details.
Highlights and visuals of the plan are below.
- Summary of Key Components for the Project
– No Upfront Cost to the District
– 1,054 high-efficiency 585-watt panels
– Lower Energy Rate Secured Long-Term
– Non-Renewable Energy Cost Savings
– Minimal Impact During Construction
– Strong Environmental Impact
– Fully Operational by Late Summer 2025
Project Overview
Wilmette Park District has launched an innovative solar panel project at the Community Recreation Center, our most active and energy-intensive facility, as part of a broader commitment to environmental responsibility and operational sustainability. This initiative aligns with the District’s Comprehensive and Sustainability Plans, marking a significant milestone in its ongoing efforts to reduce reliance on traditional energy sources and embrace cleaner, greener alternatives.
As stewards of community resources and public spaces, the Park District leads by example, demonstrating how renewable energy solutions can serve environmental and economic priorities. By making “green choices” today, the District is laying the groundwork for a healthier, more sustainable future.
Project Partners and Their Roles
Wilmette Park District: We identified the need for a long-term energy solution and the Recreation Center as a great facility to utilize for this project. The District will benefit directly from the energy savings and reduced environmental impact.
Onyx Renewables: Serving as the third-party owner and financier, Onyx Renewables is responsible for funding, installing, and maintaining the entire solar array. Through a Power Purchase Agreement (PPA) with the District, Onyx will sell the generated solar electricity at a fixed rate—lower than the District’s current utility cost—ensuring long-term savings without upfront investment.
Verde Solutions: As the energy consultant for the project, Verde Solutions provided technical expertise, feasibility analysis, and project coordination. Their insights helped shape system specifications and long-range savings projections, including an estimated $50,981 in annual non-renewable energy cost offset, and $1.54 million in lifecycle savings over 25 years.
Planning Goal and Intended Outcomes
Implement a solar energy solution that aligns with the Wilmette Park District’s Comprehensive and Sustainability Plans.
Reduce reliance on non-renewable energy sources by generating over 717,000 kWh of clean electricity annually.
Secure a third-party partnership to finance, install, and maintain the solar system with no upfront capital cost to the District.
Lock in long-term electricity rates below current market prices to ensure predictable budgeting and mitigate future utility cost increases.
Minimize disruptions to Recreation Center operations, parking, programming, and community access throughout the installation process.
Utilize facility rooftop space efficiently to house a high-capacity solar system without reducing usable program space.
Achieve long-term operational savings, with an estimated $50,981 in annual non-renewable energy cost offset and $1.54 million over 25 years.
Enhance the Park District’s reputation as a sustainability leader and community role model.
Create educational opportunities for residents and students to learn about renewable energy.
Documents and Presentations
No Current Documents at this Time
Project Timeline
Check back for full Project Timeline
December 2023
Project Concept Begins
Initial project plans conceived with Verde and ONYX.
Winter 2024
Planning Begins
Facility assessments with electrical and structural engineers.
Spring 2024
Determine how many panels could fit at the CRC and which electrical service could accommodate.
June - December 2024
Approvals
Received necessary approvals from Verde, ONYX, Project Engineers, Roofing Supplier and the Village of Wilmette.
Winter 2025
Prep Work
Work on preparing the roof for installation.
May 2025
Project Begins
Project beings at CRC!
May 26, 2025
Solar Panel Racks Installed
Began installation of solar panel racks.
June 18, 2025
Solar Panels Installed
Began installation of solar panels.
July 14, 2025
Solar Panels Install Update
Solar Panel installation complete on roofs 1, 2 and 3.
July 21, 2025
Solar Panels Fully Installed
Solar Panel installation completed! The project is now awaiting final testing and approval by ComEd.
October 1, 2025
Solar Panels Fully Installed
Installation of a new electrical panel and cutover performed by ComEd taking place the first week of October.