Updated 4.3.26
Phase 4 – North Entrance Hallway
The CRC Restoration Project has now progressed to its final phase, which includes the closure of the north entrance hallway.
During this phase, the main sports gym entrance from the interior hallway will be closed.
Staff will be available to assist patrons with wayfinding and alternative access routes.
Phase 3 – North Hallway (Near Bathrooms)
The project has now progressed to Phase 3, which includes the closure of the north hallway just past the bathrooms.
During this phase, access to the rock garden and main courtyard doors is temporarily closed. Access to the main foyer from the North Hallway is temporarily closed.
Access to the Sports Gym and Theater available through the North Entrance. All other areas of the building should be accessible from the main entrance at the front of the building.
Staff will be available to assist patrons with wayfinding and alternative access routes.
Starting Wednesday, April 1 at 6 a.m., the CRC Restoration Project will move into its next phase of work.
Phase 2 – Gymnastics Lobby
The project is now moving into Phase 2, which will focus on the Gymnastics Lobby. This area will be closed to all access during this phase.
Staff will be available on-site to assist with directions and ensure continued access to programs.
Phase 1 Complete – Western Hallway Reopened
Phase 1 of the project has been successfully completed, and the western hallway is now fully reopened to the public. We appreciate the community’s patience during this initial phase.
CRC Restoration Project: Final Phase Update
The District is beginning the final phases of the CRC Restoration Project, with carpeting and baseboard work starting Monday, March 30.
Phase 1: Western Hallway Closure
Phase 1 will begin on March 30 and will include the closure of the western hallway, spanning from the vending machine lobby to the ECC double doors.
The remaining work will be completed in three additional phases (Gymnastics Lobby, North Hallway, North Entryway). Each phase will begin immediately following the completion of the previous phase. Updates will be shared with the community as dates and timing become clearer.
Each phase will require temporary closures and adjusted access routes within portions of the facility. Staff will be on-site to help direct patrons and ensure continued access to programs whenever possible.
We appreciate the community’s patience as we complete these final improvements to the CRC.
Work Continues
Construction work is progressing throughout the facility with various tasks including: ceiling tiles, base and transitions, countertops and cabinets. Park District staff are still building the Front Desk, with cabinetry currently in transit.
This work does not effect traffic flow in the building.
Front Desk Construction
Get excited for the new and improved Front Desk at the Community Recreation Center! Please pardon our dust while work crews finish constructing the desk – this work does not effect traffic flow in the building.
Our temporary Front Desk is still located in the vending lobby. We’ll be sure to share when work is complete and the new Front Desk is open for business!
Carpeting and Tiling
We’re pleased to share that several flooring improvements at the Community Recreation Center have now been completed.
Tile installation in the Vending Area Lobby is finished, along with new carpeting in the East Hallway. In addition, carpeting in Room 115 has been completed, as well as the carpeted area stretching from the main foyer to Room 115.
These updates continue to bring a fresh, cohesive look and improved comfort throughout the facility. We are excited to continue to share them as the project continues to develop.
Carpeting and Tiling Schedule
From February 10 through February 13, carpeting work will occur in the East Hallway, which will be closed to the public while this work is underway.
During this same period, from February 9 through February 13, tile installation will take place in the Vending Area Lobby.
Carpeting in Room 115 has been completed, marking another milestone in the CRC restoration process. We appreciate your patience and cooperation as we continue to make progress toward fully restoring the Community Recreation Center.
CRC Main Foyer Is Now Fully OPEN!
Beginning Friday, January 30, the CRC main foyer will be fully reopen to the public, providing access to all areas of the building including the main staircase and elevator.
CRC Main Foyer Reopening & Updated Building Access
The Community Recreation Center continues to make strong progress as restoration work moves forward. We are pleased to share several important access updates for patrons visiting the CRC over the next few days.
Beginning Wednesday, January 28, the CRC main foyer will partially reopen to the public, providing access to the elevator and stairway to the second floor. Additionally, the North Hallway leading to the Sports Gym and Theater is now open, allowing improved movement through the building.
The East Wing entrances remain open, and we are happy to announce that the front doors will reopen starting Thursday morning, January 29, restoring access through the primary entrance.
At this time, access to the Western Hallway from the main foyer remains temporarily closed as tiling work continues. This area is expected to fully reopen by Saturday, January 31.
CRC Main Foyer Partially Open 1/24 – Entrance Closed Through 1/28
Beginning Saturday, January 24, the CRC main foyer will partially reopen to the public, giving access to the elevator. However, the primary main entrance, the north entrance and west entrance will remain closed through Wednesday, January 28 as reconstruction work continues.
Please refer to the navigation map to find the best entry door for your destination within the CRC:
What This Means for Your Visit:
How to Navigate the Building:
Temporary Area Closure Notice | January 12–16
Due to scheduled painting work in the theater area, the Auditorium Wing of the Community Recreation Center will be closed daily from 6:00 a.m. to 2:00 p.m. from January 12 through January 16.
The Auditorium Wing will reopen for normal use each afternoon and evening. We appreciate your patience and cooperation as we complete this work.
Work continues to move forward at the Community Recreation Center with visible progress throughout the building. The main foyer and registration desk area have been fully demolished in preparation for a redesigned and more functional entrance, and this space is now awaiting reconstruction and installation. On the second floor and within the business office suite, new carpeting and baseboards have been installed, along with newly installed and waxed tile flooring throughout the second floor. In addition, rooms in these areas are actively being reconstructed and prepared to accommodate the full return of scheduled programming.
2nd Floor Hallway Closed for Carpeting: December 11 – December 12
From Thursday, December 11, through Friday, December 12, the 2nd floor hallway at the Community Recreation Center will be fully closed due to construction. This closure will affect traffic flow for 2nd floor programming and Center Fitness Club users. Please plan accordingly and allow extra time when arriving.
What This Means for Your Visit:
How to Navigate the Building:
Please refer to the navigation map to find the best entry door for your destination within the CRC:
Restoration of the Community Recreation Center (CRC) following a triggered sprinkler incident earlier this year is entering its major construction phase. In the coming months, visitors will see steady progress as crews repair affected rooms, studios, offices and common areas throughout the facility. Although temporary disruptions are expected, we aim to continue all programming and ensure a safe, welcoming environment during construction.
Restoration work has begun with contractor-led preparation and planning. Initial efforts included staging materials, coordinating logistics and preparing the building for subsequent phases.
In late November and early December, construction will focus on the second floor of the CRC. This phase will involve rebuilding walls, replacing damaged ceilings and flooring, repainting rooms and restoring specialized program spaces, including fitness studios and arts areas. During this period, access to portions of the second floor will be limited, and some programs may be relocated to available rooms within the building.
From late December through January, construction will shift to the first floor, where activity rooms, office suites and support spaces will undergo similar repairs. This work will continue through much of January and into late February. As construction moves through these areas, certain rooms may temporarily close, and staff offices and the front desk may be repositioned to accommodate work while continuing to serve the public.
In late winter, construction will address the lobby and main entrance. This phase will include replacing damaged finishes, updating flooring and enhancing the appearance of the front entryway. During this period, visitors may encounter adjusted traffic flow or temporary alternative entrances; however, the building will remain accessible.
The entire Community Recreation Center Restoration Project is scheduled for “substantial completion” in early March, at which time most spaces will be fully restored and reopened. Final touch-ups and inspections will follow. Upon completion, the Community Recreation Center will operate at full capacity, offering refreshed, safe, updated program areas for all our patrons.
We appreciate the community’s patience and understanding during these essential repairs. Our commitment is to deliver a high-quality restoration that supports the wide range of programs, activities, and services that make the CRC an integral part of Wilmette Park District. For questions or assistance regarding program locations or impacts, staff are always here to help.
To learn more about the CRC Restoration Project, please visit our project page.